Building Projects by Phase
Phase I
- Cafeteria, All Purpose Field, Track, Training Room
- Schedule: Complete, October 2018
- Budget: $9.4 million
Phase II
- Science/Math Classroom Addition
- Schedule: Awaiting State Approvals, Estimated August 2018
- Bidding: Estimated September 2018
- Construction: Estimated Start October 2018
- Completion: Estimated December 2019
- Budget: $12.4 million
Phase IIA
- JR/SR High School, Classroom Renovations, Asbestos Removals, Administrative Offices
- Schedule: State Submission Estimated November 2018
- State Approvals: Estimated June 2019
- Bidding: Estimated July 2019
- Construction: Estimated Start August 2019
- Completion: Estimated September 2020
- Budget: $2.6 million
Phase IIB
- Bank and Chorus Room Alterations/Reconstruction, HS Entry Reconstruction
Classroom Renovations, Asbestos Removal - Schedule: State Submission Estimated January 2019
- State Approvals: Estimated August 2019
- 1st Bidding: Estimated February/March 2020
- Construction: Estimated start October 2020
- Completion: Estimated April of 2021
- 2nd Bidding: Estimated November 2020
- Construction: Estimated June 2021
- Completion: Estimated October 2021
- Budget: $4.4 million
Phase III
- Bus Garage, Softball Field
- Schedule: State Submission Estimated April 2020
- State Approvals: Estimated January 2021
- Bidding: Estimated February 2021
- Construction: Estimated September 2021
- Completion: Estimated June 2022
- Budget: $2.9 million
Phase IV
- Elementary School, Nurses Room, Art Room, Parking Lot
- Schedule: Complete October 2018
- Budget: $1.3 million